[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118206":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118206,789,1,"单选题","根据标准施工招标文件，下列合同事件中承包人只能索赔工期和费用的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工过程中发现文物和古迹",true,{"key":16,"text":17,"correct":18},"B","发包人要求向承包人提前交付材料和工程设备",false,{"key":20,"text":21,"correct":18},"C","异常恶劣的气候条件",{"key":23,"text":24,"correct":18},"D","发包人原因导致试运行失败的","2021\u002F2020教材P86页 《标准施工掊标文件》中合同条款规定的可以合理补偿承包人索赔的条款 表2Z102044。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]