[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118205":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118205,789,1,"单选题","承包商承揽的某工程项目，由于业主就某项设计变更不能按时提供变更图纸，使相关工作拖延3天，导致承包商自有机械窝工10个台班，该机械台班费150元\u002F台班，台班折旧费为20元\u002F台班，该工作有3天的总时差，承包商按规定提交了索赔文件，下列说法正确的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","承包商将不能获得工期及费用补偿",false,{"key":16,"text":17,"correct":14},"B","承包商可获得适当的工期补偿及费用补偿",{"key":19,"text":20,"correct":14},"C","承包商可获得3天的工期补偿，费用补偿200元",{"key":22,"text":23,"correct":24},"D","承包商不能获得工期补偿，但可获得费用补偿200元",true,"2021\u002F2020教材P85页 总时差为3天，延误3天，所以不能索赔工期。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]