[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118202":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118202,789,1,"单选题","下列承包商增加的人工费中，不可以向业主索赔的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","特殊恶劣气候导致的人员窝工费",true,{"key":16,"text":17,"correct":18},"B","完成合同之外的工作增加的人工费",false,{"key":20,"text":21,"correct":18},"C","由于非承包商责任的工效降低而增加的人工费",{"key":23,"text":24,"correct":18},"D","监理工程师原因导致工程暂停的人员窝工费","2021\u002F2020教材P85页 人工费。包括增加工作内容的人工费、停工损失费和工作效率降低的损失费等累计，其中增加工作内容的人工费应按照计日工费计算，而停工损失费和工作效率降低的损失费按窝工费计算，窝工费的标准双方应在合同中约定。特殊恶略气候导致的人员窝工费属于不可抗力不可以索赔。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]