[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118199":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118199,789,1,"单选题","合同履行期间，由于招标工程量清单中缺项，新增分部分项工程清单项目的，应()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按照变更价款确定方法确定单价，调整合同价款",true,{"key":16,"text":17,"correct":18},"B","不予调整",false,{"key":20,"text":21,"correct":18},"C","按照计价规范的规定自行调整合同价款",{"key":23,"text":24,"correct":18},"D","按照计价规范的规定，在承包人提交的实施方案被发包人批准后调整合同价款","2021\u002F2020教材P78页 合同履行期间，由于招标工程量清单中缺项，新增分部分项工程量清单项目的，应按照变更价款确定方法确定单价，调整合同价款。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]