[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118198":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118198,789,1,"单选题","工程竣工结算书编制与核对的责任分工是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发包人编制，承包人核对",false,{"key":16,"text":17,"correct":14},"B","监理机构编制，发包人核对",{"key":19,"text":20,"correct":14},"C","造价咨询人编制，承包人核对",{"key":22,"text":23,"correct":24},"D","承包人编制，发包人核对",true,"2021\u002F2020教材P92 除专用合同条款另有约定外，承包人应在工程竣工验收合格后28天内向发包人和监理人提交竣工结算申请单，并提交完整的结算资料，有关竣工结算申请单的资料清单和份数等要求由合同当事人在专用合同条款中约定",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]