[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118196":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118196,789,1,"单选题","根据《标准施工招标文件》中通用合同条款的规定,发包人认为有必要时,由监理人通知承包人以()方式实施变更的零星工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","临时工",false,{"key":16,"text":17,"correct":18},"B","计日工",true,{"key":20,"text":21,"correct":14},"C","钟点工",{"key":23,"text":24,"correct":14},"D","计件工","2021\u002F2020教材P79页 发包人通知承包人以计日工方式实施的零星工作,承包人应予执行。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]