[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118192":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118192,789,1,"单选题","某土方开挖工程，工程量清单的工程量为2400m3，合同约定的综合单价为500元\u002Fm3，当实际工程量超过清单工程量10%时可调整单价，调整系数为0.9。工程结束时实际工程量为2800m3，则该土方工程的结算价款是()万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","139.2",true,{"key":16,"text":17,"correct":18},"B","132",false,{"key":20,"text":21,"correct":18},"C","126",{"key":23,"text":24,"correct":18},"D","127.2","2021\u002F2020教材P78页 (1)对于任一招标工程量清单项目，如果因本条规定的工程量偏差和工程变更等原因导致工程量偏差超过15%，调整的原则为：当工程量增加15%以上时，其增加部分的工程量的综合单价应予调低；但合同约定范围10%变更，即合同约定范围(10%)内的工程款为：2400×(1+10%)×500＝132万元，超过10%之后部分工程量的工程款为：[2800-2400×(1+10%)]×500×0.9=7.2万元，则工程总的结算价款为：132+7.2=139.2万元。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]