[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118191":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118191,789,1,"单选题","根据《标准施工招标文件》，下列时间中承包人可以获得工期和费用补偿，但不能获得利润补偿的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工过程发现文物",true,{"key":16,"text":17,"correct":18},"B","发包人的原因导致的工程缺陷和损失",false,{"key":20,"text":21,"correct":18},"C","异常恶劣的气候条件",{"key":23,"text":24,"correct":18},"D","发包人的原因造成工期延误","2021\u002F2020教材P86页 表2Z102035中的“施工过程发现文物、古迹以及其他遗迹、化石、钱币或物品”只能索赔工期、费用且不能索赔利润",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]