[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118189":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118189,789,1,"单选题","发生合同工程工期延误时，计划进度日期后续工程的价格应采用()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","计划进度日期与实际进度日期两者的较高者",false,{"key":16,"text":17,"correct":14},"B","因发包人原因导致工期延误时，计划进度日期后续工程的价格，采用计划进度日期与实际进度日期两者的较低者",{"key":19,"text":20,"correct":21},"C","因承包人原因导致工期延误时，计划进度日期后续工程的价格，采用计划进度日期与实际进度日期两者的较低者",true,{"key":23,"text":24,"correct":14},"D","计划进度日期与实际进度日期两者的较低者","2021\u002F2020教材P80页 因承包人原因导致工期延误的，则计划进度日期后续工程的价格，采用计划进度日期与实际进度日期两者的较低者。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]