[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118188":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118188,789,1,"单选题","根据《标准施工招标文件》，下列时间中承包人可以获得工期、费用和利润的补偿的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工过程发现文物",false,{"key":16,"text":17,"correct":14},"B","发包人的原因导致的工程缺陷和损失",{"key":19,"text":20,"correct":14},"C","异常恶劣的气候条件",{"key":22,"text":23,"correct":24},"D","发包人的原因造成工期延误",true,"2021\u002F2020教材P86页 该题主要考察的是：《标准施工招标文件》中合同条款规定的可以合理补偿承包人索赔的条款。参考表2z102044。A只能获得工期和费用补偿；B只能获得费用和利润补偿；C只能获得工期赔偿。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]