[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118187":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118187,789,1,"单选题","对于任一招标工程量清单项目，如果因本规定的工程量偏差和工程变更等原因导致工程量偏差超过（）,综合单价进行调整。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","15%",true,{"key":16,"text":17,"correct":18},"B","10%",false,{"key":20,"text":21,"correct":18},"C","20%",{"key":23,"text":24,"correct":18},"D","25%","2021\u002F2020教材P78页 已标价工程量清单中有适用于变更工程项目的，采用该项目的单价；但当工程变更导致该清单项目的工程数量发生变化，且工程量偏差超过15%,此时，调整的原则为：当工程量增加15%以上时，其增加部分的工程量的综合单价应予调低；当工程量减少15%以上时，减少后剩余部分的工程量的综合单价应予调高。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]