[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118186":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118186,789,1,"单选题","某建设工程项目施工单位在施工中发生如下人工费：完成业主要求的合同外工作花费4万元；由于业主原因导致工效降低，使人工费增加2万元；施工机械故障造成人员窝工损失2万元：为实现创优质工程要求增加1万元。则施工单位可向业主索赔的人工费为()万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","8",false,{"key":16,"text":17,"correct":14},"B","7",{"key":19,"text":20,"correct":21},"C","6",true,{"key":23,"text":24,"correct":14},"D","4","2021\u002F2020教材P85页 索赔费用中人工费包括增加工作内容的人工费、停工损失费和工作效率降低的损失费等累计。 因为4万是业主要求合同外的花费，2万是由于业主原因导致功效降低。所以索赔人工费为6万。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]