[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118184":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118184,789,1,"单选题","工程施工中，发生了不可抗力事件，导致的人员伤亡、财产损失及其费用增加，由承包人承担的是()",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","合同工程本身的损害",false,{"key":16,"text":17,"correct":14},"B","运到施工场地用于施工的材料的损害",{"key":19,"text":20,"correct":14},"C","工程所需清理、修复的费用",{"key":22,"text":23,"correct":24},"D","承包人的施工机械设备损坏",true,"2021\u002F2020教材P83页 承包人的施工设备由承包人承担；",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]