[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118182":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118182,789,1,"单选题","某新校区抗震模拟实验室工程，模拟振动台设备基础采用钢筋混凝土大块基础，混凝土施工要求使用商品混凝土。但在模拟振动器台设备基础施工中，由于业主要求从使用商品混凝土变为现场搅拌，致使工期延期3天。则承包商可索赔材料费的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","人工价格上涨",false,{"key":16,"text":17,"correct":18},"B","材料超期储存",true,{"key":20,"text":21,"correct":14},"C","材料被盗和损坏",{"key":23,"text":24,"correct":14},"D","材料进货日期变化","2021\u002F2020教材P85页 料费。包括索赔事件引起的材料用量增加、材料价格大幅度上涨、非承包人原因造成的工期延误而引起的材料价格上涨和材料超期存储费用。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]