[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118180":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118180,789,1,"单选题","某基础工程，施工合同约定的计日工每工日工资标准为40元。在基坑开挖过程中，由于业主未按合同约定履行造成承包商8人窝工5天，而承包商由于劳动力计划安排不当导致5人窝工10天，窝工费按照日工资标准的80%计算，则承包商可提出的人工费索赔为()元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1280",true,{"key":16,"text":17,"correct":18},"B","1600",false,{"key":20,"text":21,"correct":18},"C","2880",{"key":23,"text":24,"correct":18},"D","3600","2021\u002F2020教材P85页 承包商提出的人工费索赔，只包括由于业主原因造成的承包商8人窝工5天，故索赔额为：8×5×40×80%=1280元。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]