[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118178":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118178,789,1,"单选题","某独立土方工程，招标文件中估计工程量为120万m3，合同中规定：土方工程单价为6元\u002Fm3，当实际工程量超过估计工程量15%时，调整单价，单价调为4元\u002Fm3。工程结束时实际完成土方工程量为160万m3，则土方工程款为()万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","828",false,{"key":16,"text":17,"correct":14},"B","880",{"key":19,"text":20,"correct":21},"C","916",true,{"key":23,"text":24,"correct":14},"D","960","2021\u002F2020教材P78页 对任一招标工程量清单项目，如果因本条规定的工程量偏差和工程变更等原因导致工程量偏差超过15%，调整的原则为：工程量增加15%以上时，其增加的部分工程量综合单价应于调低合同约定范围内（15%以内）的工程款为：120×(1+15%)×6=138×6=828万元。超过15%之后部分工程量的工程款为：(160-138)×4=88万元。则土方工程款合计=828+88=916万元。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]