[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118177":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118177,789,1,"单选题","某混凝土工程，工程量清单中的混凝土工程量2000m3，合同约定：混凝土工程综合单价为420元\u002Fm3；当实际工程量增加或减少超过10%时可调整单价，增加超过10%时综合单价的调整系数为0.9，减少超过10%时综合单价的调整系数为1.15。工程施工过程中由于出现设计变更，承包商实际完成的混凝土工程量为2500m3。则该混凝土工程的价款为（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","75.60万元",false,{"key":16,"text":17,"correct":14},"B","94.50万元",{"key":19,"text":20,"correct":14},"C","102.90万元",{"key":22,"text":23,"correct":24},"D","103.74万元",true,"2021\u002F2020教材P78页 由于混凝土工程实际工程量超过了工程量清单的工程数量10%，其超出部分的工程量为：2500-2000×(1+10%)=300m3增加超过10%的综合单价的调整系数为0.9.故该混凝土工程的价款为：2000×(1+10%)×420+300×420×0.9=103.74万元。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]