[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118173":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118173,789,1,"单选题","某钢筋混凝土基础工程，施工合同约定采用现场搅拌混凝土方式浇筑。但在基础施工过程中，由于业主要求将现场搅拌混凝土方式变更为商品混凝土方式，致使工程延期3天，则承包商可索赔材料费的情况是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","材料损耗费",false,{"key":16,"text":17,"correct":18},"B","材料超期储存",true,{"key":20,"text":21,"correct":14},"C","材料被盗和损坏",{"key":23,"text":24,"correct":14},"D","材料进货日期变化","2021\u002F2020教材P85页 材料费。包括索赔事件引起的材料用量增加、材料价格大幅度上涨、非承包人原因造成的工期延误而引起的材料价格上涨和材料超期存储费用。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]