[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118172":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118172,789,1,"单选题","某工程招标控制价为2000万元，签订的中标价为1800万元，如果施工过程中发生已标价工程清单中没有适用也没有类似的工程变更，承包人可以根据报价浮动率提出变更工程项目的单价，报发包人确认后调整。则承包人报价浮动率应控制在（）范围内。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5%",false,{"key":16,"text":17,"correct":18},"B","10%",true,{"key":20,"text":21,"correct":14},"C","15%",{"key":23,"text":24,"correct":14},"D","20%","2021\u002F2020教材P84页 招标工程的承包人报价浮动率计算公式：承包人报价浮动率L=（1-中标价\u002F招标控制价）×100%=（1-1800\u002F2000）×100%=10%。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]