[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118171":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118171,789,1,"单选题","某工程的定额工期为300天，按照相关规定，招标人在确定合同工期时，压缩的工期天数不得超过（）天，超过者，招标人应在招标文件中明示增加赶工费用。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","30",false,{"key":16,"text":17,"correct":14},"B","45",{"key":19,"text":20,"correct":21},"C","60",true,{"key":23,"text":24,"correct":14},"D","90","2021\u002F2020教材P83页 （1）招标人应当依据相关工程的工期定额合理计算工期，压缩的工期天数不得超过定额工期的20%，超过者，应在招标文件中明示增加赶工费用",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]