[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118170":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118170,789,1,"单选题","某混凝土工程招标清单工程量为200m3，综合单价为300元\u002Fm3。在施工过程中，由于工程变更导致实际完成工程量为250m3。合同约定当实际工程量增加超过15%时可调整单价，调价系数为0.9。该混凝土工程的实际工程费用为（）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","6",false,{"key":16,"text":17,"correct":18},"B","7.44",true,{"key":20,"text":21,"correct":14},"C","7.5",{"key":23,"text":24,"correct":14},"D","8.25","2021\u002F2020教材P78页 由于混凝土工程实际工程量超过了工程量清单的工程数量15%，其超出部分的工程量为：250－200×（1＋15%）＝20m3，该部分的综合单价需要调整，故该混凝土工程的价款为：200×（1＋15%）×300＋20×300×0.9＝7.44万元。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]