[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118168":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118168,789,1,"单选题","当发生多次索赔事件以后，适宜采用( )计算索赔金额。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实际费用法",false,{"key":16,"text":17,"correct":18},"B","总费用法",true,{"key":20,"text":21,"correct":14},"C","综合费用法",{"key":23,"text":24,"correct":14},"D","修正费用法","2021\u002F2020教材P86页 (2)总费用法：即发生了多起索赔事件后，重新计算该工程的实际费用，再减去原合同价，其差额为承包人索赔的费用。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]