[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118167":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118167,789,1,"单选题","“非典”期间，有不少在建工程停工，由于这种流行性疾病属于不能预见、不能避免并不能克服的客观情况、构成不可抗力，发包人要求承包人安排管理人员及保费人员的费用原则上应由( )负担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","政府部门",false,{"key":16,"text":17,"correct":18},"B","业主",true,{"key":20,"text":21,"correct":14},"C","设计部门",{"key":23,"text":24,"correct":14},"D","承包商","2021\u002F2020教材P83页 承包人在停工期间按照发包人要求照管、清理和修复工程的费用由发包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]