[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118163":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118163,789,1,"单选题","某新校区抗震模拟实验室工程，主体部分采用钢架结构，施工合同约定钢材由业主供料，其余材料均委托承包商采购。但承包商在以自有机械设备进行主体钢结构制作吊装过程中，由于业主供应钢材不及时导致承包商停工7天，则承包商计算施工机械窝工费时，应按（）向业主提出索赔。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","机械台班费",false,{"key":16,"text":17,"correct":14},"B","机械租赁费",{"key":19,"text":20,"correct":14},"C","机械使用费",{"key":22,"text":23,"correct":24},"D","机械折旧费",true,"2021\u002F2020教材P85页 (2)设备费：因窝工引起的设备费索赔，当施工机械属于施工企业自有时，按照机械折旧费计算索赔费用。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]