[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118160":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118160,789,1,"单选题","合同工程实施期间，如果出现设计图纸（含设计变更）与招标工程量清单任一项目的特征描述不符，且由此导致工程造价增减变化的，应按（）的规定重新确定相应工程量清单项目的综合单价，调整合同价款。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实际施工的项目特征",true,{"key":16,"text":17,"correct":18},"B","设计图纸的项目特征",false,{"key":20,"text":21,"correct":18},"C","招标工程量清单",{"key":23,"text":24,"correct":18},"D","暂估价","2021\u002F2020教材P78页 承包人应按照发包人提供的设计图纸实施合同工程，若在合同履行期间，出现设计图纸（含设计变更）与招标工程量清单任一项目的特征描述不符，且该变化引起该项目的工程造价增减变化的，应按照实际施工的项目特征按规范相关条款的规定重新确定相应工程量清单项目的综合单价，调整合同价款。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]