[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118158":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118158,789,1,"单选题","某工程合同价为1000万元，合同约定：物价变化时合同价款调整采用价格指数法，其中固定要素比例为0．3，调价要素为人工费、钢材、水泥三类，分别占合同价的比例为0．2、0．15、0．35，结算时价格指数分别增长了20％、15％、25％，则该工程实际价款的变化值为（）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","125",false,{"key":16,"text":17,"correct":18},"B","150",true,{"key":20,"text":21,"correct":14},"C","175",{"key":23,"text":24,"correct":14},"D","200","2021\u002F2020教材P80页 由价格调整公式得：1000×｛0.3＋（0.2×1.2）＋（0.15×1.15）＋（0.35×1.25）－1｝＝150，故选择B。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]