[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118155":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118155,789,1,"单选题","合同工程实施期间，如果出现招标工程量清单中措施项目缺项，承包人应将新增措施项目实施方案提交发包人批准后，按照（）的规定调整合同价款。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","变更价款",false,{"key":16,"text":17,"correct":18},"B","计价规范",true,{"key":20,"text":21,"correct":14},"C","合同约定",{"key":23,"text":24,"correct":14},"D","措施项目清单","2021\u002F2020教材P78页 （3）由于招标工程量清单中措施项目缺项，承包人应将新增措施项目实施方案提交发包人批准后，按照计价规范的规定调整合同价款。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]