[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118154":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118154,789,1,"单选题","下列关于工程计量的表述，错误的是（）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程量必须以承包人完成合同工程应予计量的工程量确定",false,{"key":16,"text":17,"correct":14},"B","施工中进行工程量计量时，当发现招标工程量清单中出现缺项引起工程量增减时，应按承包人在履行合同义务中完成的工程量计量",{"key":19,"text":20,"correct":14},"C","监理人应在收到承包人提交的工程量报告后7天内完成对承包人提交的工程量报表的审核并报送发包人",{"key":22,"text":23,"correct":24},"D","超出合同工程范围施工或返工的工程量，发包人均应予以计量",true,"2021\u002F2020教材P75， 工程量必须以承包人完成合同工程应予计量的工程量确定。施工中进行工程量计量时，当发现招标工程量清单中出现缺项、工程量偏差，或因工程变更引起工程量增减时，应按承包人在履行合同义务中完成的工程量计量 监理人应在收到承包人提交的工程量报告后7天内完成对承包人提交的工程量报表的审核并报送发包人。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]