[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118153":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118153,789,1,"单选题","某工程合同价为100万元，合同约定：采用调值公式进行动态结算，其中固定要素比重为0.3，调价要素 A、 B、C分别占合同价的比重为0.15、0.25、0.3，结算时价格指数分别增长了20％、15％、25％，则该工程实际结算款额为（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","119.75",false,{"key":16,"text":17,"correct":14},"B","128.75",{"key":19,"text":20,"correct":21},"C","114.25",true,{"key":23,"text":24,"correct":14},"D","127.25","2021\u002F2020教材P78页 根据建筑安装工程费用的价格调值函数， P=100×[0.3+0.15×(1+20％)+0.25×(1+15％)+0.3×(1+25％)]可得P=114.25万元。 @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]