[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118148":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118148,789,1,"单选题","某工程项目采用单价合同，在施工过程中进行某分项工程计量时发现因工程变更，承包人实际完成的工程量超过了工程量清单中的工程量，则进行该分项工程计量时()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按照招标工程量清单中的工程量计算",false,{"key":16,"text":17,"correct":18},"B","按承包人在履行合同义务中完成的工程量计算",true,{"key":20,"text":21,"correct":14},"C","按承包人提交的已完工程量计算",{"key":23,"text":24,"correct":14},"D","按发包人核实后的工程量计算","2020版教材P75页 施工中工程计量时，若发现招标工程量清单中出现缺项、工程量偏差，或因工程变更引起工程量的增减，应按承包人在履行合同义务中完成的工程量计算。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]