[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118143":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118143,789,1,"单选题","根据《建设工程工程量清单计价规范》，以“项”为计量单位的措施项目费()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","采用工程量清单综合单价计价方式",false,{"key":16,"text":17,"correct":14},"B","包括除利润、税金外的全部费用",{"key":19,"text":20,"correct":14},"C","包括除规费、利润、税金外的全部费用",{"key":22,"text":23,"correct":24},"D","包括除规费、税金外的全部费用",true,"2021\u002F2020教材P67页 措施项目清单计价应根据建设工程的施工组织设计，对可以计算工程量的措施项目，应按分部分项工程量清单的方式采用综合单价计价；其余的措施项目可以以“项”为单位的方式计价，应包括除规费、税金外的全部费用。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]