[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118139":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118139,789,1,"单选题","在编制综合单价的时候，计算综合单价的第一步是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","将清单项目的工程内容与定额项目的工程内容进行比较",true,{"key":16,"text":17,"correct":18},"B","测算人料机消耗量",false,{"key":20,"text":21,"correct":18},"C","计算定额子目工程量",{"key":23,"text":24,"correct":18},"D","确定人料机单价","2021\u002F2020教材P65页 因此计算综合单价的第一步就是将清单项目的工程内容与定额项目的工程内容进行比较.",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]