[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118137":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118137,789,1,"单选题","工程量清单中分部分项工程量的确定依据是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程量清单编制人按施工图图示尺寸和清单工程量计算规则计算得到的工程净量",true,{"key":16,"text":17,"correct":18},"B","工程量清单编制人按实际施工方案和清单工程量计算规则计算得到的工程净量",false,{"key":20,"text":21,"correct":18},"C","工程投标人按实际施工方案和清单工程量计算规则计算得到的工程净量",{"key":23,"text":24,"correct":18},"D","工程投标人按施工图图示尺寸和清单工程量计算规则计算得到的工程净量","2021\u002F2020教材P64页 分部分项工程量的确定依据是：招标文件中的工程量清单标明的工程量是招标人编制招标控制价和投标人投标报价的共同基础，它是工程量清单编制人按施工图图示尺寸和清单工程量计算规则计算得到的工程净量。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]