[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118134":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118134,789,1,"单选题","确定分部分项工程和措施项目中的单价项目综合单价的最重要依据之一是清单的()",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目名称",false,{"key":16,"text":17,"correct":14},"B","项目编码",{"key":19,"text":20,"correct":14},"C","项目计量单位",{"key":22,"text":23,"correct":24},"D","项目特征描述",true,"2021\u002F2020教材P71页 确定分部分项工程和措施项目中的单价项目综合单价的最重要依据之一是清单项目的特征描述",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]