[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118133":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118133,789,1,"单选题","根据国家标准《建设工程工程量清单计价规范》（GB50500-2008），工程量清单中的其他项目清单不包括（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","总承包服务费",false,{"key":16,"text":17,"correct":14},"B","材料暂估价",{"key":19,"text":20,"correct":14},"C","暂列金额",{"key":22,"text":23,"correct":24},"D","规费",true,"2021\u002F2020教材P69页 其他项目费由暂列金额、暂估价、计日工、总承包服务费等内容构成。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]