[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118130":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118130,789,1,"单选题","根据现行《建筑安装工程费用项目组成》GB50500-2013，下列措施项目适合采用分包法计价的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","室内空气污染测试",true,{"key":16,"text":17,"correct":18},"B","夜间施工费",false,{"key":20,"text":21,"correct":18},"C","二次搬运费",{"key":23,"text":24,"correct":18},"D","冬雨期施工的计价","2021\u002F2020教材P69页 参数法的有：夜间施工费、二次搬运费、冬雨期施工的计价 在分包价格的基础上增加投标人的管理费及风险费进行计价的方法，这种方法适合可以分包的独立项目，如室内空气污染测试等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]