[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118129":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118129,789,1,"单选题","招标文件中的工程量清单标明的工程量是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按施工图图示尺寸和清单工程量计算规则计算得到的工程净量",true,{"key":16,"text":17,"correct":18},"B","承包人在履行合同义务中应予完成的实际工程量",false,{"key":20,"text":21,"correct":18},"C","设计文件结合不同施工方案确定的工程量均值",{"key":23,"text":24,"correct":18},"D","工程实体量和损耗量的合计","2021\u002F2020教材P64页 招标文件中的工程量清单标明的工程量是招标人编制招标控制价和投标人投标价的共同基础，它是工程量清单编制人按施工图图示尺寸和清单工程量计算规则计算得到的工程净量。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]