[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118128":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118128,789,1,"单选题","根据《建设工程工程量清单计价规范》GB50500-2013编制投标文件时，招标文件中提供了暂估单价的材料，应按（）计入综合单价。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","投标时的市场价格",false,{"key":16,"text":17,"correct":14},"B","投标人自主确定的价格",{"key":19,"text":20,"correct":21},"C","按暂估的单价",true,{"key":23,"text":24,"correct":14},"D","政府主管部门公布的价格","2021\u002F2020教材P72页 招标文件中提供了暂估单价的材料，按暂估的单价计入综合单价。 暂估价即为招标文件工程量清单中提供的价格。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]