[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118125":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118125,789,1,"单选题","在施工过程中必须发生，但在投标时很难具体分项预测的二次搬运费和冬雨期施工费用的计价适宜采用（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","实物量法",false,{"key":16,"text":17,"correct":14},"B","综合单价法",{"key":19,"text":20,"correct":21},"C","参数法",true,{"key":23,"text":24,"correct":14},"D","分包法","2021\u002F2020教材P69页 2.参数法计价此段最后一句：夜间施工费、二次搬运费、冬雨期施工的计价均可以采用该方法",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]