[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118124":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118124,789,1,"单选题","根据《建设工程工程量清单计价规范》GB50500-2013，招标文件中要求投标人承担的风险费用，投标人应（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在投标总价的基础上加上一定比例",false,{"key":16,"text":17,"correct":18},"B","在综合单价中给予考虑",true,{"key":20,"text":21,"correct":14},"C","在总承包服务中给予考虑",{"key":23,"text":24,"correct":14},"D","在其他项目费中给予考虑","2021\u002F2020教材P72页 招标文件中要求投标人承担的风险费用，投标人应在综合单价中给予考虑，通常以风险费率的形式进行计算。风险费率的测算应根据招标人的要求结合投标企业当前的风险控制水平进行定量测算。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]