[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118123":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118123,789,1,"单选题","在计算工程量清单项目的综合单价时，应将该清单项目合价除以（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","清单工程量",true,{"key":16,"text":17,"correct":18},"B","复核工程量",false,{"key":20,"text":21,"correct":18},"C","清单工程量与复核工程量的均值",{"key":23,"text":24,"correct":18},"D","实体工程量","2021\u002F2020教材P66页 （7）将清单项目的人、料、机费、管理费及利润汇总得到该清单项目的合价，将该清单项目合价除以清单项目的工程量即可得到该清单项目的综合单价。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]