[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118120":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118120,789,1,"单选题","措施项目费的计算方法中，( )计价适用于可以计算工程量的措施项目，主要是指一些与工程实体有紧密联系的项目。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","综合法",true,{"key":16,"text":17,"correct":18},"B","测定法",false,{"key":20,"text":21,"correct":18},"C","参数法",{"key":23,"text":24,"correct":18},"D","分包法","2021\u002F2020教材P69页 综合单价法：根据需要消耗的实物工程量与实物单价计算措施费，适用于可以计算工程量的措施项目，主要是指一些与工程实体有紧密联系的项目。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]