[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118119":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118119,789,1,"单选题","对于夜间施工费，采用工程量清单计价宜采用（）的方法",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","综合单价法",false,{"key":16,"text":17,"correct":18},"B","参数法计价",true,{"key":20,"text":21,"correct":14},"C","分包法计价",{"key":23,"text":24,"correct":14},"D","全费用综合单价","2021\u002F2020教材P69页 参数法计价是指按一定的基数乘系数的方法或自定义公式进行计算。这种方法简单明了，但最大的难点是公式的科学性、准确性难以把握。这种方法主要适用于施工过程中必须发生，但在授标时很难具体分项预测，又无法单独列出项目内容的搢施项目。如夜间施工费、二次搬运费、冬雨期施工的计价均可以采用该方法。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]