[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118117":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118117,789,1,"单选题","对于其他项目中的计日工，投标人正确的报价方式是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","待签证时报价",false,{"key":16,"text":17,"correct":18},"B","自主报价",true,{"key":20,"text":21,"correct":14},"C","按政策规定标准估算报价",{"key":23,"text":24,"correct":14},"D","按招标文件提供的金额报价","2021\u002F2020教材P72页 (3)计日工应按照其他项目清单列出的项目和估算的数量，自主确定各项综合单价并计算费用。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]