[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118116":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118116,789,1,"单选题","某工程，招标人提供的工程量清单中挖土方的工程量为3000m3，投标人根据其施工方案计算出的挖土方作业量为3500m3，完成该分项工程的人工、材料、机械费为70000元，管理费为15000元，利润为4000元，其他因素均不考虑，则根据已知条件，投标人应报的综合单价为()元\u002Fm3。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","24.29",false,{"key":16,"text":17,"correct":14},"B","25.43",{"key":19,"text":20,"correct":14},"C","28.33",{"key":22,"text":23,"correct":24},"D","29.67",true,"2021\u002F2020教材P66页 综合单价=（人、料、机费＋管理费＋利润）\u002F清单工程量=(70000＋15000＋4000)\u002F3000=29.67元\u002Fm3。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]