[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118115":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118115,789,1,"单选题","某工程根据清单规则计算的挖方量为2500m3，根据地质资料和施工方案计算需人工挖土方量为5000m3，人工挖土单价为8.4元／m3，机械运土方量为2000m3，机具费单价为20元／m3，管理费取人、料、机费的14%，利润取人、料、机与管理费之和的8%。根据建筑工程量清单计算规则计算该土方工程的综合单价为()元／m3。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","20，19",false,{"key":16,"text":17,"correct":14},"B","32,80",{"key":19,"text":20,"correct":21},"C","40.38",true,{"key":23,"text":24,"correct":14},"D","45.36","2021\u002F2020教材P66页 综合单价=人工费+材料费+施工机具使用费+管理费+利润。人、料、机费合计=人工挖土人、料、机费+机械运土人、料、机费=5000m3×8.4元／m3+2000m3×20元／m3=82000元，管理费=82000元×14%=11480元，利润=（82000元+11480元）×8%=7478.4元，总计费用=82000元+11480元+7478.4元=100958.4元，工程量清单综合单价=100958.4元\u002F2500m3=40.38元\u002Fm3。 公式为：=(5000*8.4+2000*20)*(1+14%)*(1+8%)\u002F2500",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]