[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118108":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118108,789,1,"单选题","某施工工序的人工产量定额为4.56m3，则该工序的人工时间定额为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.22工日\u002Fm3",false,{"key":16,"text":17,"correct":18},"B","0.22工日",true,{"key":20,"text":21,"correct":14},"C","1.76工日\u002Fm3",{"key":23,"text":24,"correct":14},"D","4.56工日\u002Fm3","2021\u002F2020教材P61页 时间定额是某种专业、某种技术等级工作班或个人，在合理的劳动组织和合理使用材料的条件下，完成单位合格产品所必需的工作时间。包括准备与结束时间。基本工作时间，辅助工作时间。不可避免的中断时间及工作必需的休息时间。时间定额与产量定额之间的关系是：时间定额-1\u002F产量定额，则时间定额-1\u002F产量定额-1\u002F4.56-0.22工日。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]