[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118106":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118106,789,1,"单选题","编制施工机械合班使用定额时，施工机械必须消耗时间包括有效工作时间、不可避免的中断时间以及( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工本身造成的停工时间",false,{"key":16,"text":17,"correct":14},"B","非施工本身造成的停工时间",{"key":19,"text":20,"correct":14},"C","低负荷下的工作时间",{"key":22,"text":23,"correct":24},"D","不可避免的无负荷工作时间",true,"2021\u002F2020教材P62页 在必需消耗的工作时间里，包括有效工作，不可避免的无负荷工作和不可避免 的中断三项时间消耗。 @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]