[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118105":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118105,789,1,"单选题","对于施工条件正常、产品稳定、工序重复量大、统计制度健全的施工过程，确定其人工定额时间可以采用()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","统计分析法",true,{"key":16,"text":17,"correct":18},"B","技术测定法",false,{"key":20,"text":21,"correct":18},"C","比较类推法",{"key":23,"text":24,"correct":18},"D","经验估计法","2021\u002F2020教材P60页 确定人工定额的方法包括技术测定法、统计分析法、比较类推法、经验估计法。其中统计分析法适用于施工条件正常、产品稳定、工序重复量大和统计工作制度健全的施工过程。 @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]