[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118102":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118102,789,1,"单选题","已知某挖土机挖土的一个工作循环需2分钟，每循环一次挖土0.5m3，工作班的延续时间为8小时，时间利用系数K=0.85，则该机械的产量定额为()m3／台班。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","12.8",false,{"key":16,"text":17,"correct":14},"B","15",{"key":19,"text":20,"correct":21},"C","102",true,{"key":23,"text":24,"correct":14},"D","120","2021\u002F2020教材P63页 该挖土机械的小时生产率为60\u002F2×0.5=15m3，则其产量定额为15×8×0.85=102m3\u002F台班。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]